|
There are two ways to do justifications: rule of thumb and fully
detailed. The decision of which method to use depends on the
nature of the justification. Using the rule-of-thumb methods, a
fairly standard annual capacity number is 70 percent. If you are
looking to demonstrate the need for adding capacity, take the
ideal number of available hours (hours per day available times
number of days running per year) and reduce that ideal by
multiplying by .70. This number takes into account a stable
operation (one that is increasing capacity by adding days or
shifts) and routine maintenance for tooling and machinery, and may
leave a little room for the unplanned. This number is conservative
if your shop has long runs of the same product. Conversely, a
short-run shop with multiple material and tool changes may work
hard to reach 70 percent.
The complete capacity or cost/benefit analysis approach uses as
much information as you can gather about a specific project. Cost
items to consider include the following: the initial purchase
price; loan, buy, or lease costs; operating expenses (electricity,
shop overhead for the specific area o the new equipment,
lubricants, and fluids); spare parts inventory; shipping, rigging,
and installation costs; new auxiliary equipment costs; and
training expenses. Using these items instead of a standard machine
rate requires more work but it separates costs into categories
that can be studied for specific issues rather than setting press
expense rates. This list usually covers the majority of costs and
financial professionals will be happy to explain these numbers, or
at least give them to you. The difficult part is demonstrating how
spending this money benefits the company more than spending it
elsewhere, or simply investing it.
You need additional information to calculate a return or
justify the investment. If your justification is for capacity only
(there are no make or buy issues and no speculative investments)
you will be comparing overtime costs to new equipment costs on
standard time. How much does it cost to run overtime? Do you need
two people per shift to run an automatic operation? Is there a
general increase in absenteeism when overtime becomes routine?
If you are meeting requirements with one or two days of
overtime, a new press will give you two to five times the capacity
you need. What will you do with the extra machine time? Are there
sales opportunities that have been bypassed because you didn't
have the capacity? Asking questions like these may give you
several payback items that normally do not appear on a
justification sheet.
If you need to justify a new project, or wish to make an
investment in capacity, the issue is more complicated. As a
general list, you need the estimated cost of the products to be
produced, the quantity to be produced, and the time frame for
delivery. Separate the costs into categories such as material,
factory overhead, labor, packaging, and so forth. Know which parts
of the cost picture are related to the new equipment.
In a complete new project, the numbers are fairly
straightforward. Is there more income than expense? At a minimum,
this is an annual sales vs. total expenses question, not a single
order issue. Say a new project has a per thousand parts profit of
$50, but only runs for two months of the year. Does that $50 pay
for the idle equipment? If there is idle time available, is it
salable or completely lost? How fast can it realistically be sold?
Does getting this work increase the work for the other equipment?
If so, the additional revenues should be part of the
justification. I have seen where adding one 20 percent-utilized
machine increased existing equipment usage by 50 percent. With the
additional information, even the accountants were excited.
The third need for justification is to replace old equipment.
Here you will need to treat the differences between old and new as
the income. Make a spreadsheet with cost items, a column for each
machine, and a difference column. How much less does it cost to
run the new machine on an hourly basis (ask the equipment vendor
for actual data, not vague promises)? How much additional uptime
can be expected from the reduction in maintenance? Have you run a
trial in the new machine at the vendor's location? If so, did
existing tooling run faster or produce less scrap? You will need
additional lines in your spreadsheet to show these savings. I
recommend showing either a per-part or per-thousand parts line and
then showing the annual savings. If running faster eliminates
overtime, include all relevant overtime costs. On one project we
replaced 48 inspectors and manual equipment with one optical CMM,
produced statistical data, improved throughput by 10 percent in
manufacturing, and reduced defect-related rejections for a total
savings of $250,000. - R. Caufman, RC Marketing Inc., (814)
726-7442, rcmktg@penn.com.
|
|