|
I've used the following process to chase down balance in larger
fans. Other than machine conditions, the only other variable not
within your control is glass content percentage. Have ready access
to a dynamic balance machine with suitable resolution. Install a
cavity pressure sensor with the necessary machine controls and
develop a comfortable process window. Next, lock on controls for
peak cavity pressure and fill time and wait 24 hours to measure
the imbalance amount. Then make corrections to the mold (add
balance lugs). The imbalance amount and location will change as
the impeller absorbs moisture. You can restart the mold with
controls on peak cavity pressure and fill time. Remember that it's
important to have identical conditions on all other parameters.
Measure imbalance as soon as the impeller cools and fits
properly on the balance arbor. Check imbalance amount and location
and note that this imbalance data should be used as a benchmark
predictor for "dry as-molded samples." To get impellers
within specification after 24 hours, you may have an as-molded
balance target that is out of specification. Measure imbalance on
the same samples after 24 hours. If everything repeats, you should
be within the balance tolerance. Good Luck. - B.Daly, PTA Corp.,
Oxford, CT (203) 888-0585, bdaly@ptacorp.com.
Machine capability is key. Even minute variation in shot size,
fill (rates and times), and heat can lead to balance
inconsistencies. I recommend a capability study that includes the
following three features: part weight, imbalance, and angle of
imbalance in parallel with critical machine parameters. Please
note that the angel of imbalance is very important. Unless the
angle is stable, balancing the part is virtually impossible. Once
the three part features are in control you can permanently balance
the part by adding material at the respective balance planes and
monitoring the molding machine parameters. - J. Wagner, Westplex
Industries Corp., Manchester, NY (716) 289-3630, westplexjimw@yahoo.com.
Here are some of the things I check when problems like this
arise, but, like all things, the key is finding the right
combination. First check the stock wall of the tool and then check
the gating system because you may need to adjust the gates. The
nylon being used will set up quickly. You should also check the
barrel heats for consistent temperature. This material produces a
lot of gas so maybe try using a slower fill. You can try backing
down on the tonnage to allow the gas to escape the tool. Also,
make sure the material is properly dried. You may want to try
running the material higher than normal, profiling your barrel
heats, and using a nylon tip if you can. If I can be of further
help feel free to write me. - S. Clay, Ferriot Inc., Akron, OH,
(330) 786-3000, sclay@ferriot.com.
The mold should have three balance adjusting pins approximately
1/4 inch in diameter that can be moved into or out of the part as
much as .100 inch. Once the tool has been tuned in (with the three
points specific for balance set at its midpoint), single plan
balance readings are taken on the part when an equilibrium process
has been reached. Then the required pin adjustments can be
calculated and the whole procedure repeated until satisfactory
balance has been attained. It is not a short or easy job and the
tolerance on the balance must be realistic, perhaps about .006
inch for the part as described. - W. Foster, Tessy Plastics Corp.,
Elbridge, NY, (315) 689-2077, bfoster@tessy.com.
Run short shots to see if all the impeller parts are filling
uniformly every time. If one side is filling first it will be
heavier. If you are gating into the hub then you may have to add
more gates to get a balanced flow. Once you get a consistent and
uniform filling, all of the parts should have the same balance
characteristics. Any imbalance can be corrected with judicious
metal removal. - F. French, Amitima, Manchester, MO (314)
522-1252.
Gating is the key. Generally speaking, when you're dealing with
something that's round and filling radiates out from the center,
it is crucial to use a membrane gate. That gate is in the center
of the impeller and tends to fill from the center of the part. To
locate the gate on one end of a hub would actually be improper.
You want to locate the gate down into the depth of the part,
preferably where the melt starts to flow into any of the ribs that
radiate out from the center of the hub. You want that impeller to
fill evenly from the center-out to have adequate venting. I
suggest a gate thickness of .040 inch, .030 inch minimum;
otherwise, the gate can get plugged by lumps of glass, which
interferes with the even distribution of the polymer. If it's a
big impeller, you require a thicker gate. Then you do a secondary
operation to shear out the gate after ejection. - E. Barno,
Multiform Plastics, Sterling Heights, MI, (810) 726-2688,
multiform@ameritech.net.
Equip your tool with pressure transducers and your machine with
an eDart monitor from RJG Inc. Real-time process data will tell
you whether the part is good or bad. We have had success balancing
fill on an eight-drop hot manifold with RJG's technology. - J.
Schramzki, Acra Inc., Traverse City, MI, (231) 947-8733, jims@acrainc.com.
|
|